Houlton is a development to the east of Rugby with permission for the delivery of 6,200 homes together with a district centre, local centres, open space, secondary school and primary schools. It also provides space for retail, financial services, restaurants, a hotel, community uses, assembly and leisure, as well as commercial and employment uses. 

The planning strategy for the development is based on a three-tiered approach as follows:  

Tier 1. Outline permission was granted in 2014 and updated in 2017.  Land uses and the amount of development were defined together with site wide strategies, design principles and parameter plans. It sets out that the site will be developed in a series of ‘Key Phases’.  

Tier 2. Requires each Key Phase to be defined and then followed with a framework including a Design Guide and technical documents.    

Tier 3. Reserved Matters applications for the detailed design of development within a Key Phase. 

Details for Key Phases 1, 2, 3 and 4 have been approved to date. Development is underway in each of these Key Phases pursuant to a number of Reserved Matter approvals. 

Development Framework Plan for Houlton

The approved Development Framework Plan for Houlton is not fixed and guaranteed. Elements of this plan have already changed and will be subject to further changes as detailed development proposals come forward.

More information

Outline Permissions 

The 2017 outline permission can be found under reference R17/0022. It can be accessed at https://planning.agileapplications.co.uk/rugby/application-details/24928  

The 2014 outline permission can be found under reference R11/0699. It can be accessed at https://planning.agileapplications.co.uk/rugby/application-details/10925

Design Guides 

Regulatory Plans 

Applications 

There have been over 170 applications at Houlton. These can be accessed at https://planning.agileapplications.co.uk/rugby/search-applications/. In the “Location” field enter “Houlton” to find all applications relating to this area. If you are looking for an application within a particular Key Phase enter “Key Phase [1, 2, 3 or 4] Houlton” in the “Location” field.