Current progress
Latest - March 2024
Willmott Dixon has now completed enabling works, with site accommodation and hoarding established.
Vegetation has been removed from the site, while piling for the development's four apartment blocks has started and looks set to be completed within four weeks.
Next steps include the piling for the development's houses, completing the installation of storm and foul drainage, and the construction of the new road to the site.
Work on the site's sub-structures looks set to start next month.
The development should be completed in January 2026.
Willmott Dixon delivers a regular newsletter to near neighbours of the site detailing the development's progress.
Construction operations hours are 07:30 to 18:00 Mon-Fri, and 08:30 to 13:00 Saturday. Access to the site for all construction traffic will be directly off Clifton road.
Biart Place
Clifton Road
Rugby CV21 3RE